Real jobs from the plants we serve, plus one emergency call. We don’t name clients. Every Gem crew is foreman-led.

Pharma & Life Sciences

Clean room expansion against a hard turnover date

A life-science manufacturer in North Jersey, working under the general contractor (2026)

The challenge

The clean room expansion had a fixed turnover date. The electrical scope covered a new airlock and washroom, power to the clean room and its process equipment, and three fume hoods with hazardous-location requirements. It also meant shutting down the old clean room and working inside a live one.

What Gem did

  • Fed VFDs on the mezzanine, vacuum pumps, ultrasonic, argon and freeze-dryer equipment, and the RO2 system on 480V three-phase.
  • Used stainless-steel disconnects and stainless rigid conduit and hardware, plus rooftop disconnects.
  • Installed explosion-proof seal-offs, IS barrier grounding and intrinsically safe airflow-sensor wiring at the three fume hoods, and worked out the IS details with the hood vendor.
  • Installed grounding panels, mag-lock interlocks with override push buttons, sliding doors, exit signs, lighting and ceiling sensors.
  • Cleaned every screw and tool with alcohol before it went into the live clean room.
  • Closed out with arc-flash labels and panel schedules, plus the fire-alarm final test.

Result

The above-ceiling inspection passed, the room turned over on the client’s date in early September, and the job closed out with labels and panel schedules in place.

Clean room corridor with glass doors, green interlock lights, push-to-enter station and exit sign
Stainless control panel in a clean room with HEPA ceiling
Door interlock indicator light and switch plates on a clean room wall
Clean room build-out with ceiling grid and lighting installed
Stainless-steel disconnect switch installed in a clean room

More on our pharma & life sciences work →

Food Processing

A 30-foot wash-down cold room on a short schedule

A private food service company serving major U.S. airline hubs

The challenge

The client needed a new cold room built and an existing room migrated into it once it was complete. The room is 30 feet high and a complete wash-down area, which made it hard to maneuver. The schedule was short, and the client added many items along the way.

What Gem did

  • Set a plan of attack at the start and adjusted it as conditions changed.
  • Did the electrical for the new 30-foot-high wash-down cold room.
  • Used NEMA 4X enclosures and stainless steel and aluminum conduit and equipment, with enclosures and equipment mounted on standoffs off the wall for wash-down compliance, as we do on every food job.
  • Migrated the existing room into the new one once it was complete.
  • Re-planned each time the client added items, and kept going through many 12-hour days.

Result

We delivered an active room for the client.

New cold room with pallet racking, LED lighting and scissor lifts
Wall-mounted electrical device on standoffs off the wall for wash-down compliance

More on our food processing work →

Planned Shutdowns

Planned shutdown: two breakers, one window, no slip

A facility in North Jersey

The challenge

The facility allows only two scheduled shutdowns a year, and the last two were called off for weather. The scope was a new 800A breaker in the main switchgear lineup and a 3-pole 70A breaker downstream, both in aging switchboard gear, with no live tie-ins allowed.

What Gem did

  • Walked the job again and walked the plan with building leadership.
  • Caught one unavailable material item, which our office sourced from an alternate supplier on time.
  • Tested every tool beforehand, catching a crimper with a dead trigger.
  • In the window, installed both breakers, ran conduit and wire, and landed terminations.

Result

The facility was back up on schedule. Shutdowns are won in the days before.

More on our capabilities →

Emergency & After-Hours

Same-night power restoration after roof work damaged a plant’s wiring

Semiconductor equipment manufacturer, New Jersey

The challenge

Late in the afternoon, the production area lost power during a roof replacement. A main switchgear breaker had tripped, taking down two 480V panels and three 120/208V transformers, and second shift couldn’t run without lights or power.

What Gem did

  • We redirected crews already on the road. Instead of resetting the breaker, they found the cause first: roofers had driven screws through several conduit runs installed in the roof structure, which is an older practice that today’s code doesn’t allow. The crew de-energized and locked out the area, removed the damaged conduit, re-terminated the wiring at existing and new junction boxes, then re-energized the switchgear and panels one step at a time.

Result

Six damaged circuits across three panels were repaired, including a 480V rooftop unit feed, in about six hours. Power was back by about 11 PM, and the plant started first shift on time the next morning.

Screw driven through a vertical conduit, with a burn mark on the pipe
Screw through a horizontal conduit run, with a burned wire inside
New EMT and junction box installed under the roof deck

More on our emergency & after-hours work →