Case studies
Real jobs from the plants we serve, plus one emergency call. We don’t name clients. Every Gem crew is foreman-led.
Pharma & Life Sciences
Clean room expansion against a hard turnover date
A life-science manufacturer in North Jersey, working under the general contractor (2026)
The challenge
The clean room expansion had a fixed turnover date. The electrical scope covered a new airlock and washroom, power to the clean room and its process equipment, and three fume hoods with hazardous-location requirements. It also meant shutting down the old clean room and working inside a live one.
What Gem did
- Fed VFDs on the mezzanine, vacuum pumps, ultrasonic, argon and freeze-dryer equipment, and the RO2 system on 480V three-phase.
- Used stainless-steel disconnects and stainless rigid conduit and hardware, plus rooftop disconnects.
- Installed explosion-proof seal-offs, IS barrier grounding and intrinsically safe airflow-sensor wiring at the three fume hoods, and worked out the IS details with the hood vendor.
- Installed grounding panels, mag-lock interlocks with override push buttons, sliding doors, exit signs, lighting and ceiling sensors.
- Cleaned every screw and tool with alcohol before it went into the live clean room.
- Closed out with arc-flash labels and panel schedules, plus the fire-alarm final test.
Result
The above-ceiling inspection passed, the room turned over on the client’s date in early September, and the job closed out with labels and panel schedules in place.





Food Processing
A 30-foot wash-down cold room on a short schedule
A private food service company serving major U.S. airline hubs
The challenge
The client needed a new cold room built and an existing room migrated into it once it was complete. The room is 30 feet high and a complete wash-down area, which made it hard to maneuver. The schedule was short, and the client added many items along the way.
What Gem did
- Set a plan of attack at the start and adjusted it as conditions changed.
- Did the electrical for the new 30-foot-high wash-down cold room.
- Used NEMA 4X enclosures and stainless steel and aluminum conduit and equipment, with enclosures and equipment mounted on standoffs off the wall for wash-down compliance, as we do on every food job.
- Migrated the existing room into the new one once it was complete.
- Re-planned each time the client added items, and kept going through many 12-hour days.
Result
We delivered an active room for the client.


Planned Shutdowns
Planned shutdown: two breakers, one window, no slip
A facility in North Jersey
The challenge
The facility allows only two scheduled shutdowns a year, and the last two were called off for weather. The scope was a new 800A breaker in the main switchgear lineup and a 3-pole 70A breaker downstream, both in aging switchboard gear, with no live tie-ins allowed.
What Gem did
- Walked the job again and walked the plan with building leadership.
- Caught one unavailable material item, which our office sourced from an alternate supplier on time.
- Tested every tool beforehand, catching a crimper with a dead trigger.
- In the window, installed both breakers, ran conduit and wire, and landed terminations.
Result
The facility was back up on schedule. Shutdowns are won in the days before.
Emergency & After-Hours
Same-night power restoration after roof work damaged a plant’s wiring
Semiconductor equipment manufacturer, New Jersey
The challenge
Late in the afternoon, the production area lost power during a roof replacement. A main switchgear breaker had tripped, taking down two 480V panels and three 120/208V transformers, and second shift couldn’t run without lights or power.
What Gem did
- We redirected crews already on the road. Instead of resetting the breaker, they found the cause first: roofers had driven screws through several conduit runs installed in the roof structure, which is an older practice that today’s code doesn’t allow. The crew de-energized and locked out the area, removed the damaged conduit, re-terminated the wiring at existing and new junction boxes, then re-energized the switchgear and panels one step at a time.
Result
Six damaged circuits across three panels were repaired, including a 480V rooftop unit feed, in about six hours. Power was back by about 11 PM, and the plant started first shift on time the next morning.